312 Uhdali Place Loudon, Tennessee 37774
Phone: 865-635-1618
E-mail: twharrison1122@gmail.com
Objective
Objective includes
obtaining a senior level project controls position in the Engineering,
Procurement, Construction, and commissioning areas where demonstrated skills
and experience will contribute to profitable operations for the company.
Career goals include being a major factor of a project team leading to
positive job achievements and successful and safe project completions.
Career profile
An accomplished
professional with comprehensive experience and knowledge of project controls
that can assist in engineering, procurement, outage, construction and
commissioning planning phases with experience in Nuclear, Fossil Fuels, and
Petro-Chemical projects. Proactively assess progress trends and completion
forecasts, and provides solutions to mitigate unfavorable circumstances or to
optimize project objectives. Other skills include project planning and
estimating for initial project / program schedule development. Management and
Supervisory experience in project and organizational based teams.
Skills summary
v
Performs schedule development, maintenance,
and monitoring activities
v
Performs data analysis, identifies problems,
and makes recommendations
v
Assists in the development and execution of
earned value trending and reporting
v
Supervises and provides technical direction
for planning / scheduling and cost engineering when delegated
v
Assists in developing unit man-hour and
pricing data for specific disciplines or other specialties, including
estimating parameters, factors, indices, productivity and craft distribution
reference data, etc. based on analysis of industry experiences
v
Develop and Deploy Project / Program Earned
Value Management Systems
v
Monitors schedule deviation / proposes
corrective actions for project variances
v
Assists in the development of KPI’s (Key
Performance Indicators)
v
Assists in the development of Project
Deliverables (Internal / Customer based)
v
Develops quantity release or installation
curves for assigned disciplines or specialties
v
Executive Level / Project Level Dashboard
Development
v
Assists in leveling decisions
v
Assists in cash flow reporting / leveling
v
Performs deliverable / quantity manpower
loading for assigned schedules & projects
v
Develops expert level custom Crystal Reports
v
Advanced Excel / VBA / Code Query Builder /
Automated Metric Development
Positions Held
October 2012 -
Present
Tennessee Valley
Authority / Nuclear Power Group Chattanooga, TN
Senior Project
Controls Specialist - Lead Analyst for NPG / BFN NFPA 805 Program
Developing Program
processes and Project Controls Strategies for Implementation utilizing Earned
Value Management and Risk Analysis for On-line and Outage MODS
Implementation. Related responsibilities include:
v
Monitor and Forecast Costs against the
approved funding package
v
Monitor and forecast costs against the yearly
budget
v
Develop and monitor project schedules to
assure committed dates
v
Manage resources to assure required work is
accomplished on schedule and within Budget
v
Develop / Implement Vendor Project Controls
Terms & Conditions
v
Manage contingent workforce needed to
complete the NFPA 805 Transition Projects
v
Manage the various managed task contracts
with the NFPA 805 vendors
v
Develop change management / implementation
plan to minimize the negative impact of Program Roll-out
and Execution
Primarily manage the
scope, schedule, and costs associated with the approved projects
Experience with
schedules in excess of 10,000 + activities. Advanced Oracle Primavera P6
vers. 7 Excel, Access, Power Point, Adobe, Maximo, and Cognos software
programs utilized
March 2012—August
2012
Tennessee valley
authority / watts bar nuclear station
spring city,
Tennessee
lead project controls
coordinator- developed and implemented methods for performance monitoring,
reporting, analysis, and trend assessment. Facilitate programs to ensure
establishment and analysis of specific operational and process improvement
plans used for goal setting, estimating project plans, performance
indicators/targets, benchmarking, and trending, including tracking daily
cost/progress/earned value/CPI/SPI, spend plans and EACs. Coordinate
Engineering A/E contracts, monitor contract expenditures for usage trends,
assist in the process of issuing new contracts, amending existing contracts,
and resolve questions, issues, etc. Lead/manage the process ensuring the
integrity of the process, resolving pending/outstanding requests, reconciling
encumbrances and pending tasks with IBS as required. Experience with
schedules in excess of 10,000 + activities. Primavera P3 and Advanced Oracle
Primavera P6 version. 7 Excel, Access, Power Point, Adobe, PeopleSoft,
Maximo, Business Objects, and Passport software programs utilized.
November 2011- March
2012
Southern Company
Nuclear operating – Birmingham, Alabama
Contracted ESS
Primavera / Maximo Nuclear Fleet Analyst for Daily On-line and Outage
Scheduling. Responsible for fleet analysis of work and asset management
scheduling supporting three (3) operating nuclear stations. Perform analysis
of schedule baselines, and producing forecast analysis reporting. Develop
tracking and trending of project status; anticipate problems and ADVISES team
of issues / metric development; perform variance and critical path analysis.
Responsible for developing Fleet Performance Indicators for Fleet Scheduling
performance areas such as Scope Stability in T-minus timeframes, Emergent
Work, Schedule Adherence, and Schedule Stability according to INPO Standards
97-005, AP-928, and AP-925. Act as a consultant to the project team for
scheduling and work management issues. Experience with schedules in excess of
15,000 + activities. Advanced Oracle Primavera P6 vers. 7 Excel, Access,
Power Point, Adobe, PeopleSoft, Maximo, Business Objects, and Passport
software programs utilized
May 2011—october 2011
Mitsubishi nuclear
energy systems – fort mill, south Carolina
Lead Project
Scheduler for the North Ana Unit 3 USAPWR Project. Ensure that the Project
Master Schedule complies with Contractual and Quality Control / Quality
Assurance programs and procedures. Developed and maintained Project Controls
processes and desktop guidelines for all in-house and subcontractor partners.
Responsible for the adherence and utilization of the project Work breakdown
and Cost breakdown components and usage. Attention to detail including
critical path analysis, work flow analysis, resource leveling and cash flow
analysis (SAP), but not limited to the following; Planning, coordinating, and
managing all schedule and control activities on multiple projects using
Primavera Project Manager, 6.0 version7, Interface with various internal and
external stakeholders on project planning and scheduling related items and
functions including reporting requirements, progress reporting, earned value,
and key project deliverable trending. Represent project team in team meetings
with project stakeholders as required regarding project performance related
to schedule and controls. Experience and analysis with project schedules in
excess of 100,000 + schedule activities. Perform additional assignments as
directed
February 2011 – may
2011
areva nap NSSS
tennessee valley authority – Bellefonte nuclear station Hollywood, Alabama
Site Lead Scheduler –
NSSS Programs /
Projects
Lead Scheduler
capacity for work in a very large program including multiple projects and
contracts. Plans and advises on implementation strategies for new projects
within the program. Monitors and analyses the project plans, mobilization of
manpower, schedules, progress, and resources utilization and recommends
corrective actions. Ensures that the planning and scheduling documents such
as, master schedules, progress reports, and PROGRESS Metrics (Earned Value)
and bar charts are prepared properly and in accordance with contractual time
schedules and frequencies by consultants / contractors. Prepares the planning
formats and scope of work with respect to program control. Reviews project
execution strategies and implementation schedules for new projects developed
by the project team and advice on logic, duration and mode of implementation.
Identifies and reviews the critical and sub-critical activities and their
impact on the project schedules. Monitors the reported progress of consultants/contractors
and ensures that the reports accurately reflect the actual performance and
productivity. Oracle Primavera 6.1 version 7 utilized, along with
Excel, Access, Power Point, Adobe and SAP programs.
November 2010 –
february 2011
duke energy / oconee
nuclear station seneca, south carolina
Oconee Major Projects
Group – Main Steam Isolation Valve Replacement (MSIV) Lead Scheduler
Responsible for the
detailed schedule development, analysis and preparations for weekly updating
cycles for the Engineering, Design, and Installation of the Main Steam
Isolation valve project (MSIV) for all three units. Responsibilities include
preliminary project cost / WBS, and detailed schedule development. Developed
multi discipline schedules for modifications and refueling outage windows in
accordance with applicable procedures and scheduling guidelines. Member
of the Major Projects Group Earned Value implementation team. EPC project
estimate +/- $420-450 million price range. Experience with schedules in
excess of 6,000 plus activities. Primavera 3.1 and Oracle Primavera 6.1
utilized, along with Excel, Access, Power Point, Adobe programs.
November 2009 –
november 2010
Bechtel Power
Services / nuclear division spring city, tennessee
Watts Bar U2
Completion Project – Senior Project Controls Engineer
Supported overall
planning & schedule development, analysis and reporting efforts for the
project. Participated in the integration of Engineering, Procurement, and
Construction schedules. Lead planning and coordinating schedule interfaces
with the owner, vendors and subcontractors. Supported the timely preparation
and update of detailed execution schedules, resource utilization plans and
progress tracking systems. Supported the integration of all activity
sequences & logic with the total project plan. Supports accurate
schedules, resource, quantities, progress, and performance reporting.
Continually monitored critical and near critical path work and identified
issues for mitigation. Proactively assessed progress, completion forecasts
and provides solutions to mitigate schedule delays or to optimize project
completion. Evaluated project progress against historical indicators and
provides management with comparative analysis. Supported the implementation
of scheduling & progress metrics and monitoring systems. Primavera
3.1, P5, and P6.1 software utilization, along with Excel, Access, Power
Point, Adobe, Business Objects, Maximo, and SAP software programs utilized.
Experience with schedules in excess of 50,000 + activities.
march 2009 – november
2009
alstom power
services / suwanee, georgia
Senior Regional
Project Controls Coordinator
Responsible for the
development and periodic re-assessment of the overall project controls
framework; to ensure that sufficient financial, operational, and compliance
related controls are in place to mitigate project risks. Perform various
activities regarding the development and analysis of project budgets and
forecasts. Perform budget versus actual variance analysis.
Prepare responses to complex data requests in terms of Earned Value Metrics,
and overall Project Schedule and Financial status. Develop, recommend, and
implement methodologies to create and maintain project budgets and forecasts
as per approved project baselines. Responsible for the development and
implementation of Project Controls applications, processes, guidelines, and
procedures for Regional and District offices along the Gulf and Atlantic
Coasts. Advanced Primavera P3, P6, Lotus, Excel, Access, Power Point,
Adobe, Timberline, and JD Edwards software programs utilized.
march 2008 – march
2009
FirstEnergy
Generation Corporation / corporate hq Akron, Ohio
Senior Outage Project
Controls Coordinator
Developed and
monitored multi discipline schedules for modifications and refueling
outages. Experience with schedules in excess of 40,000 + activities.
Outage Scheduling: Primarily worked with the planning, clearance
coordination, maintenance, engineering and operations work window managers to
determine the best effort in maximizing resources during the scheduled
outage. Lean & Six Sigma practices utilized. Advanced Primavera 3.1 and
P5, Excel, Access, Power Point, Adobe, PeopleSoft, Maximo, Business Objects,
SAP, and Passport software programs utilized.
January 2006 – march
2008
Allegheny Energy
Supply Greensburg, Pennsylvania
Senior Site Outage
Project Controls Coordinator- Outage Work Management Group
Responsible for
providing total cost and schedule control support for coal-fired power
station outages for capital and special maintenance projects; implementing
cost and schedule control processes for maintenance outages, programs and
projects; and served as lead controls person who coordinated work with power
station management, contractors, engineers and support personnel. Advanced
Primavera 3.1 and P5, Excel, Access, Power Point, Adobe, PeopleSoft, Maximo,
Business Objects, SAP, and Passport software programs utilized. Experience
with schedules in excess of 10,000 + activities.
janaury 1999 –
november 2005
American Electric
Power Service Corporation Columbus, Ohio
Senior Scheduling
Coordinator – Outage and Maintenance Planning Group
Responsibilities
include the overall program status responsibility for internal project
planning /scheduling functions on plant engineering and major environmental
projects. Schedule plans include engineering, procurement, construction /
outage and commissioning plans as integrated subprojects. Identification of
engineering, procurement, and outage / construction trends for impact on
projects critical path. Co-Chair for the implementation of performance
measurement analysis on corporate levels (Cost Performance and Schedule
Performance Indices). Responsibilities also include constant interface
between engineering, project management, plant operations and construction
management and related disciplines to facilitate and report project status.
Advanced Primavera and P3e, Lotus, Excel, Access, Power Point, Adobe, Maximo,
PeopleSoft, CTR, Business Objects, Passport and Microsoft Project software
programs utilized.
june 1990 – june 1996
Fluor Nuclear
Services Greenville, South CAROLINA
Pipefitter /Welder on
domestic refueling and Maintenance Outages
june 1984 – may 1990
Duke Power Company /
McGuire Nuclear Station Cornelius, North Carolina
Pipefitter /Welder –
Construction & Maintenance Division North (CMD)
Education and Certifications
1984 Graduate –
Buffalo Putnam Senior High School Buffalo, West Virginia
Plumbers and Pipe
fitters Joint Apprenticeship Training Program Charlotte, North Carolina
Duke Power Company /
McGuire Nuclear Station
Cornelius, North
Carolina
v
Nuclear Power generation training program
v
Various maintenance training programs
v
Basic radiation worker training program
v
Maintenance planning techniques
American Electric
Power Service Corporation
Corporate
Headquarters Columbus, Ohio
v Situational Leadership Training phases I and II
v Supervisory Training Theories sessions I and II
v Introduction to Project Management Body of Knowledge Principals
Critical Business
Analysis
Corporate Training
and Development
Perrysburg, Ohio
v User Certification – Primavera P6 project management scheduling
software
(102Basic and 106P,
106R Advanced courses)
Consultants in Data
Processing (CDP)
Charlotte, North
Carolina
Advanced training in
the following areas; Project Management, Project Controls, Cost Estimating
and Cost Accounting solutions.
User certification in
P6 advanced theory and scheduling techniques
FirstEnergy Nuclear
Operating Company (FENOC)
Akron, Ohio
v Nuclear Power generation training program
v Various maintenance training programs
v Basic radiation worker training program
v Maintenance planning techniques
v Outage Planning & Scheduling
Oversight
Member – Project Management Institute (PMI) –
Currently in study phase for PMP Designation
References are available upon request
|